In-Principle Declared NHs

In-Principle Declared National Highways

Abstract of In-Principle" Declared National Highways
Sr. No. Description Nos. Length (in Kms)
1 Total In-Principle approved NHs 69 Nos.  4312
2 DPRs to be prepared by PWD 63 Nos. 4031
3 Letter of Acceptance issued to Consultants 58 Nos. 3706
4 Alignment report submitted to MoRTH 54 Nos 3482.6
5 Draft Alignment Reports submitted by the Consultants and are under scrutiny  04 Nos 223.5
6 Tender based estimates returned unapproved by MoRTH on 18.09.2018. However ACS(PW) has requested Secretary MoRTH for reconsideration vide letter dated 20.09.2018.  04 Nos. 153
7 Tender based estimate sent to MoRTH for approval on 19.07.2018 (Earlier entrusted with BRO) 01 No.  172
Total:-  63 Nos. 
8 DPRs being prepared by NHIDCL 03 Nos.  170
9 Roads already constructed to NH standards by HPRIDC & case sent to MORTH for declaring these roads as NHs  02 Nos.  80
10 Road alignment already covered in 63 Nos roads  01 No.  30
Status of DPRs of "In Principle" declared National Highways
S.No. Name of Road Length (km) Status
1 Bhota NH-103-Jahu-Kalkhal-Ner Chowk on NH-154 52.50 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3404-10 dated 05.09.2018.
2 Rohru-Tikkar-Reog Ghatti-Nera Ghatti-Bhali Dhar-Bareon-Panog-Kiari-Deori-Kotkhai on NH-705 80.00 ÔÇó Draft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/5223-28 dated 15.12.2018
3 Chhailla on NH-705 Sainj-Oachghat-Sarahan on NH -907A 108.00 ÔÇó Draft alignment report forwarded by CE(NH) to MoRTH on 08.12.2018
4 Lowasa Chowki on NH-907A- Kolanvala-Budh-Majari Naryangarh. 46.00 Tender based estimate returned unapproved by MoRTH on 18.09.2018. However ACS(PW) has requested Secretary MoRTH for reconsideration vide letter dated 20.09.2018.
5 Shimla(Taradevi)-Kunihar-Ramsher-Nalagarh-Dharowala(HP)-Ghanauli on NH-205. 102.35 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3404-10 dated 05.09.2018.
6 Salhech- Chandol- Habbon- Rajgarh-Baddu Sahib - Bagthan- Banethi  127.30 ÔÇóFeasibility study under progress ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 18.09.2018.
7 Dadour-Chailchowk-Janjehli-Chhatri-Ranbag-Nagan (Including Tunnel ) 111.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
8 Narkanda - Baghi - Ghanasidhar-Khadrala-Sungri-Rohru-Hatkoti 40.00 Tender based estimate returned unapproved by MoRTH on 18.09.2018. However ACS(PW) has requested Secretary MoRTH for reconsideration vide letter dated 20.09.2018.
9  Ghanasidhar to Tikkar 14.00 ÔÇó Draft Alignment Report submitted to MORT&H, New Delhi vide this office letter No: PW-CE(NH)/'In-Principle' Declared NHs/Volume-VI/6237-42 dated 30.01.2019.
10 Sungri-Taklech-Nogli on NH-5  14.00 Tender based estimate returned unapproved by MoRTH on 18.09.2018. However ACS(PW) has requested Secretary MoRTH for reconsideration vide letter dated 20.09.2018.
11 Hamirpur-Sujanpur-Alampur-Palampur 60.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH on 07.09.2018
12 Basoli on NH-503 A to Biru-Thana kalan-Bangana- Nadaun on NH-3 65.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH on 12.10.2018
13 Nadaun-Tira Sujanpur-Sandhol-Kandapattan-Jogindernagar junction with NH-154  127.30 ÔÇóFeasibility study under progress ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 26.09.2018.
14 Mandawala on NH-105 Junction with Haryana-Barotiwalla-Patta-Kuthar-Arki-Shallaghat. 79.40 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
15 Shimla(Dhalli)-Tattapani-Churag-Rohanda-Sundarnagar 180.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH on 07.09.2018
16 Junction with NH-154 at Dramman- Sihunta-Chowari-Jot- Chamba-koti-Tissa-Killar. 271.00 ÔÇó Feasibility study under progress ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE/NH/In-Principle-2018-3221-23 dated 25.08.2018
17 Sanaura(NH) - Rajgarh - Nohradhar-Haripurdhar - Rohnahat - Jamali on NH-707 114.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 18.09.2018.
18 Solan to Oachghat 10.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 18.09.2018.
19 Sataun (NH-707)- Renuka-Dadahu-Jamta-Dosarka (NH-907A) 56.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
20 Haripurdhar-Sangrah-Renuka-Trimti-Bailya-Dholakuana 79.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
21 Kandaghat-Sadhupul-Chail - Kufri  57.00 ÔÇóFeasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3404-10 dated 05.09.2018.
22 Haripur Dhar-Kupavi-Tarahan-Sarahan-Chopal 67.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3404-10 dated 05.09.2018.
23 Sainj (NH-705)-Deha-Chopal- Nerwa-Feduspul(NH) 90.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
24 Solan-Subathu-Kainchi Mor 23.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 18.09.2018.
25 Kunihar to Domehar to piplughat to Dhundan to Bharirighat 33.00  ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 18.09.2018.
26 Kofota-Jakhana-Jong-Tunia-Haripur. 29.75  ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3404-10 dated 05.09.2018.
27 Yashwantnagar - Gaura - Dubloo - Janedghat  38.00  ÔÇó Draft Alignment report submitted by the Consultant and under scrutiny.
28 Chhalanda-Junga-Mehli 28.00  ÔÇó Draft Alignment report submitted by the Consultant and under scrutiny.
29 Patsari to Mandhol-Tahu-Throlla-Kotkhai 61.50  ÔÇó Draft Alignment report submitted by the Consultant and under scrutiny.
30 Nalagarh on NH-21A Dabhotta, Tibbi, Dugri-Pated Nawagram, Androla, Uperla, Kashmirpurm Baruna, Bagheri, Khatiwala Maura on NH-21 35.50  ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 18.09.2018.
31 Rohru-Chirgaon-Tikri-Larrot-Chanshal-Dodrakawar 96.00  ÔÇó Draft Alignment Reports submitted by the Consultants and are under scrutiny.
32 Junction with NH-303 at Jawallamukhi-Dehra-Jwali-Raja-Ka-Talab-Jasure. 90.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH on 07.09.2018
33 Ghatsani-Shilha-Badhani-Bhubu Jot- Kullu 52.40 ÔÇó Feasibility study under progress.
ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH on 07.09.2018
34 Dharampur-Maddi-Sandhol to Gaddidhar to Tihra to Awahdevi on NH-70 (New NH-03). 88.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3404-10 dated 05.09.2018.
35 Baijnath- Balada- Kandapattan-Dharmpur 40.50 ÔÇó Feasibility study under progress.
ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH on 07.09.2018
36 Sundernagar-Chai-Dohara-Trifalghat-Palasi. 42.00 ÔÇó Feasibility study under progress ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 18.09.2018.
37 Jogindernagar to Bareru to Dharman to Kunkatarto Kotli. 44.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 26.09.2018.
38 Declaration of Palampur-Dharamsala road via Nagri road as new National Highway. 35.70 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 26.09.2018.
39 Nagni-Pudwa-Panhar-Khundiyan-Jawalamukhi road. 34.20 ÔÇó Feasibility study under progress ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 26.09.2018.
40 Dhaneta-Barsar-Shahtalai-Berthin. 61.00 ÔÇó Final alignment report forwarded by CE(NH) to MoRTH on 19-04-2018.
ÔÇó Feasibility study under progress.
41 Bharwain-Chintpurni-Jorbar-Pucca Tiala-Sansarpur Terrace. 88.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH on 12.10.2018
42 Ranital to Masroor Lunj ÔÇô 32 Meel via Kuther Tripal Bhater Bassa Lunsu Dhar road km 0/0 to 53/500 including bridge over Baner khad. 54.20 ÔÇó Feasibility study under progress
ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 26.09.2018.
43 Kaloha-Pragpur-Dhaliara-Dada Siba Sansarpur Terrace road. 60.90 ÔÇó Feasibility study under progress .ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 26.09.2018.
44 Bhager- Panol-Berthin- Ghoridhabiri-Maharal-Bijhari-Salooni-Galore-Kangu-Lalari (Bhatha). 71.20 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
45 Didwin Tikkar-Mahal Bhoranj-Chandruhi Tatahar (Sarkaghat). 28.80 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
46 Bangana- Dhaneta- Kangu- Rangas-Balduhak- Jihan Road (Via BanganaDhaneta Tunnel) 27.80 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH on 07.09.2018
47 Santokhgarh-Tahliwal-Polian Jajon-Haroli-Saloh-Ispur-Gagret-Daulatpur-Mubarikpur-Marwari (Punjab Border) road. 97.30 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
48 Ajouli Santokhgarh Una Lower Lalsingi upto Swan Bridge. 22.20 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
49  Dadhol to Swara to Muhana to Lanjta Matiyal to Kuther road 16.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH on 07.09.2018
50 Thapna (Four lane junction)- Baghchhal (Babkhal) Marotan-Jejwin-Kalot-Bharoli kalan- Gharan Shah Talai (Including Bridge at Babkhal over Satluj River). 42.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
51 Darla Mod (Navgaon) to Berri road 37.00  ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 18.09.2018.
52 Bangana to Jawalaji via Shantla-Tutroo-Peer-Saluhi-Chamukha-Kaleshawar Mahadev. 39.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
53 Bijhari-Deotsidh ÔÇôRailly-Jajri-Bhallu Bridge-Berthin-Sunhani-Ghumarwin 51.80 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH on 07.09.2018
54 Manpul-Gauna-Basaral-Dhaneta-Tipper-Fahal-Galore-Budhawin Chowk Nalti- Hamirpur (Junction of Hamirpur Bye-Pass). 50.50 ÔÇó Feasibility study under progress.ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
55 Hamirpur (Mattan Sidh) Dosarka-Lambloo Tarakwadi-Bhoranj-Jahoo. 34.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
56 Bassi (On Navgoan Beari Road) Jabbal- Rani Kotla-Markand (Construction of Tunnel near Bandla Dhar connecting Bilaspur) Balh Bhulana- Beri Darolan (Construction of bridge connecting Kiratpur-Ner Chowk Expressway). 22.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
57 Salapad to Harnoda to Kasol to Tatapani on left bank. 64.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter dated 26.09.2018.
58 Sunni to Luhrion left bank 50.00  ÔÇó Feasibility study under progress.ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3404-10 dated 05.09.2018.
59 Kanchimore-Shree Naina Devi Ji-Bhakra 50.00 ÔÇó Feasibility study under progress. ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3320-30 dated 30.08.2018
60 Pandoh to Bakhrot via Devigarh, including tunnel at Devigarh, Masogal, Khyalpuri  81.00 ÔÇó Feasibility study under progress ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3990-94dated 3.10.2018
61 Moviseri to Rohangalu 35.00 ÔÇó Feasibility study under progress ÔÇóDraft alignment report forwarded by CE(NH) to MoRTH vide office letter no. - PW/CE(NH)/'In-Principle' Declared NHs/Vol-/V/3990-94dated 3.10.2018
62 Tandi to Sansari Nalla (with Border Roads) 172.00 ÔÇó Tender Based sent to MORTH on dated 19.07.2018
63 Lowasa Chowki on NH-907A Jaman ki Ser Dhangiar-Tikri-Kathar-Preet Nagar-Pinjore on NH-05 53.00 Tender based estimate returned unapproved by MoRTH on 18.09.2018. However ACS(PW) has requested Secretary MoRTH for reconsideration vide letter dated 20.09.2018.
DPR's not to be prepared by STATE PWD
64 Ranital on NH 503-Kotla on NH 154 39.20 Road already constructed to NH standards by HPRIDC & case sent to MORTH for declaring these roads as NHs. 
65 Ghumarwain-Jahu-Sarkaghat 41.50 Road already constructed to NH standards by HPRIDC & case sent to MORTH for declaring these roads as NHs.
66 Hathithan(NH-21)-Manikaran-Pulga 43.00 Draft DPR is being prepared by National Highway Infrastructural Development Corporation Limited.
67 Taklesh-Sarahan-jeori 77.00 Draft DPR is being prepared by National Highway Infrastructural Development Corporation Limited.
68 Chandigarh-Karoran-Tanda-Prempura-Gariran-Paploha-Bar-shilukhurd-Jangesh-Kasauli-Dharmpur (on NH-5) 50.00 Draft DPR is being prepared by National Highway Infrastructural Development Corporation Limited.
 
69 Naina Devi-Swarghat 30.00 Road length is common with 'in- principle' approved NH namely Kanchimore-Shree Naina Devi Ji-Bhakra road and moreover Swarghat to Kainchimore road is part of NH-205
  TOTAL 4311.80  