From the year 2001-02 onwards 191 no. projects have been sanctioned under CRIF amounting to Rs.2442.18 crores, out of which 154 No. projects have been completed, 6 No. projects sent for de-sanction, 5 Nos projects closed due to execution under HPRIDC and remaining 32 Nos. projects are in progress. An expenditure amounting to Rs. 151128.99 lacs has been incurred upto 31-03-2025 against the total release of funds amounting to Rs.133659.89 lacs. The brief year wise financial status is as under:-
Sr. No. |
Year |
No. of Projects Sanctioned |
Amount of A/A (Rs. in lacs) |
Funds released (Rs. in lacs) |
Exp. during the Year (Rs. in lacs) |
1 |
2000-01 |
- |
- |
348.00 |
- |
2 |
2001-02 |
7 |
1922.02 |
394.55 |
671.05 |
3 |
2002-03 |
4 |
880.67 |
1189.02 |
1186.06 |
4 |
2003-04 |
11 |
2573.29 |
630.32 |
659.92 |
5 |
2004-05 |
3 |
591.68 |
975.00 |
1196.32 |
6 |
2005-06 |
8 |
2570.75 |
1316.00 |
1183.05 |
7 |
2006-07 |
2 |
424.95 |
1216.00 |
1039.69 |
8 |
2007-08 |
4 |
1280.00 |
1548.00 |
1105.05 |
9 |
2008-09 |
7 |
5200.00 |
436.00 |
1001.04 |
10 |
2009-10 |
4 |
7330.87 |
1206.00 |
2086.72 |
11 |
2010-11 |
5 |
4543.00 |
1744.00 |
2436.00 |
12 |
2011-12 |
0 |
0.00 |
2604.00 |
2880.34 |
13 |
2012-13 |
0 |
0.00 |
2307.00 |
3130.67 |
14 |
2013-14 |
6 |
4893.00 |
2480.00 |
3381.10 |
15 |
2014-15 |
14 |
5559.00 |
0.00 |
3654.25 |
16 |
2015-16 |
44 |
19701.00 |
9473.00 |
2990.39 |
17 |
2016-17 |
0 |
0.00 |
5541.00 |
4836.39 |
18 |
2017-18 |
27 |
41979.00 |
9287.00 |
9721.42 |
19 |
2018-19 |
26 |
46636.00 |
9256.00 |
10751.63 |
20 |
2019-20 |
0 |
0.00 |
9681.00 |
11279.45 |
21 |
2020-21 |
0 |
0.00 |
9595.00 |
14919.86 |
22 |
2021-22 |
13 |
23795.00 |
18800.00 |
19152.00 |
23 |
2022-23 |
1 |
10331.00 |
16905.00 |
19610.00 |
24 |
2023.24 |
5 |
29493.00 |
13632.00 |
15023.00 |
25 | 2024.25 | 6 | 34514.00 | 13096.00 | 17223.59 |
|
Total |
197 |
244218.23 |
133659.89 |
151128.99 |
CRF work sanctioned during year 2024-25
ISC works (Inter State Connectivity)
Government of
From the year 2005-06 onwards 8 no. projects have been sanctioned under ISC amounting to Rs.11909.44 lacs out of which 7 No. projects have been completed upto 31/03/2024 and expenditure amounting to Rs.7784.21 lacs has been incurred upto 31/03/25. The brief year wise financial Status is as under:-
Sr. No. |
Year |
No. of Projects Sanctioned |
Amount of A/A (Rs. in Lacs) |
Funds Released (Rs. in Lacs) |
Exp. during the Year (Rs. in Lacs) |
1 |
2005-06 |
2 |
1033.57 |
- |
- |
2 |
2006-07 |
1 |
462.83 |
- |
394.13 |
3 |
2007-08 |
- |
0.00 |
189.00 |
785.97 |
4 |
2008-09 |
- |
0.00 |
991.00 |
280.52 |
5 |
2009-10 |
1 |
273.00 |
- |
0.00 |
6 |
2010-11 |
- |
0.00 |
- |
0.00 |
7 |
2011-12 |
- |
0.00 |
- |
248.65 |
8 |
2012-13 |
- |
0.00 |
- |
0.00 |
9 |
2013-14 |
1 |
1746.63 |
- |
0.00 |
10 |
2014-15 |
1 |
3742.59 |
- |
300.01 |
11 |
2015-16 |
1 |
2537.82 |
- |
726.99 |
12 |
2016-17 |
- |
0.00 |
- |
1457.50 |
13 |
2017-18 |
1 |
2113.00 |
- |
1602.85 |
14 |
2018-19 |
- |
0.00 |
0.00 |
820.00 |
15 |
2019-20 |
- |
0.00 |
0.00 |
725.40 |
16 |
2020-21 |
- |
0.00 |
0.00 |
442.19 |
17 |
2021-22 |
- |
0.00 |
0.00 |
0.00 |
18 |
2022-23 |
- |
0.00 |
0.00 |
0.00 |
19 |
2023-24 |
- |
0.00 |
0.00 |
0.00 |
20 | 2024-25 | - | 0.00 | 0.00 | 0.00 |
|
Total |
8 |
11909.44 |
1180.00 |
7784.21 |